File #: 25-2655    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 6/16/2025 In control: City Council
On agenda: 6/24/2025 Final action:
Title: RESOLUTION NO. 2025-9464 - APPROVING AMENDMENTS TO PROFESSIONAL SERVICES CONTRACTS WITH VILLA CIVIL AND 4LEAF INC., RESPECTIVELY, AND AUTHORIZING THE CITY MANAGER TO FINALIZE AND EXECUTE CONTRACT AMENDMENTS AND RELATED DOCUMENTS
Attachments: 1. Reso_Final

MEETING DATE:                                          

JUNE 24, 2025

 

SUBJECT:                                            

Title

RESOLUTION NO. 2025-9464 - APPROVING AMENDMENTS TO PROFESSIONAL SERVICES CONTRACTS WITH VILLA CIVIL AND 4LEAF INC., RESPECTIVELY, AND AUTHORIZING THE CITY MANAGER TO FINALIZE AND EXECUTE CONTRACT AMENDMENTS AND RELATED DOCUMENTS

Body

 

Recommendation
Recommendation

ADOPT a resolution amending the professional services contracts with Villa Civil and 4leaf Inc., and authorizing the City Manager or delegated designee to finalize and execute the contract amendments and related documents.

 

Body

Board or Commission Action

Not applicable

 

Relevant Council Strategic Theme

Planning for the Future

Good Governance

 

Relevant Department Goal

Not applicable

 

Executive Summary

To assist with the management of the Creek Infrastructure Project (Project) the City utilizes the professional services of Villa Civil and 4 Leaf Inc. to support staff in the performance of duties related to the Project. Although construction work has concluded, work relating to close-out of the project continues. The proposed increases to the existing contracts will allow for ongoing support to staff to finalize, audit and close-out the Project.

 

Discussion

The City has an existing contract with 4Leaf Inc., to provide professional services related to construction management and support for the Project. Additionally, the City has a contract with Villa Civil to provide professional extension of staff services to assist in the management of the Project. The proposed amendments would provide support as staff finalizes, audits, and closes out the Project. Due to delays in completion of the Project, claims and other close-out activities are required to be resolved. City staff currently anticipates that an additional six months of services would be required, necessitating an amendment for the 4Leaf Inc. contract in the amount of $150,000 and an amendment for the Villa Civil contract in the amount of $300,000 to provide necessary support as these close-out activities and claims are resolved. Staff therefore recommends the amendment of the 4Leaf Inc, and Villa Civil contracts in the amounts indicated.

 

Fiscal Impact 

The cost of professional services as reflected by these amendments are included within the existing Capital Improvement Program Budget.

 

 

Attachment(s)
Resolution

 

 

Prepared/Submitted by:  Isaac Etchamendy, P.E., City Engineer/Development Services Director

Approved by:  Michelle Bender, City Manager