Title: RESOLUTION NO. 2024-9378 - APPROVE AN AMENDMENT TO CONTRACT 6176 WITH SEMA CONSTRUCTION AND AUTHORIZING THE CITY MANAGER TO FINALIZE AND EXECUTE THE SAME, AND APPROVING AN AMENDMENT OF THE FY 2024/2025 CAPITAL IMPROVEMENT PROGRAM (CIP) BUDGET FOR THE CREEK INFRASTRUCTURE PROJECT (CIP NOS. 88264, 88265)
Attachments: 1. Resolution 2024-XXXX Amending Budget and Contract, 2. 88264 update, 3. 88265 update

MEETING DATE:                                          

November 12, 2024

 

SUBJECT:                                            

Title

RESOLUTION NO. 2024-9378 - APPROVE AN AMENDMENT TO CONTRACT 6176 WITH SEMA CONSTRUCTION AND AUTHORIZING THE CITY MANAGER TO FINALIZE AND EXECUTE THE SAME, AND APPROVING AN AMENDMENT OF THE FY 2024/2025 CAPITAL IMPROVEMENT PROGRAM (CIP) BUDGET FOR THE CREEK INFRASTRUCTURE PROJECT (CIP NOS. 88264, 88265)

Body

 

Recommendation
Recommendation

ADOPT a resolution amending the contract 6176 with SEMA Construction and amending the CIP Program Budget for the Creek Infrastructure Project.

 

Body

Not Applicable

 

Relevant Council Strategic Theme

Quality of Life

Good Governance

 

Executive Summary

Give some background on the topic

 

Discussion

Large construction projects typically have proportionally larger overhead cost for office staff, management, construction trailers, and general activities relating to activities that support the project. For this reason, the City bid the Creek Infrastructure Project (Project) requiring the contractor to identify the cost of Time Related Overhead (TRO) as a separate bid item. The use of TRO is a common industry standard practice and was chosen as a method of bidding for these elements on the Project.  As a result, the City has a fixed cost it will pay for additional time on the project should additional working days be granted to the contractor. Similarly, several other bid items on the project are time dependent due to the scale of the project, such as stormwater maintenance.

 

The Creek Infrastructure Project began construction in spring of 2020. Over the course of construction, the City encountered delays due to environmental constraints, unforeseen conditions, weather, and predominantly third-party utilities. The City issued a change order to SEMA in the amount of $1,478,956 for initial delays due to utility relocations through the start of the Bent Avenue bridge. Subsequent to the construction of Bent Avenue, the Project was subject to additional delays. When delays occur, the City is obligated to compensate for extension of working days where the delay is considered to be out of the contractor’s control and as supported by the contract documents. Examples of compensable delay can include waiting for outside agencies or companies to complete work, additional work required by the City.

 

Analysis of the delays has shown that the contractor is eligible to receive 112 compensable days through the completion of the Via Vera Cruz bridge. Compensable days have been analyzed pursuant to the contract terms through an analysis of the critical path construction schedule. To pay for the proposed compensable days, the Project budget and contract with SEMA would need to be amended. The proposed change orders to compensate for delays through the completion of Via Vera Cruz total approximately $2,000,000. Staff recommends the Project budget and contract with SEMA Construction be increased by the amount need to compensate for the delays.

 

Environmental Review

The activity performed under this action is not a “Project” as defined under Section 15378 of the CEQA Guidelines; and, is therefore not subject to environmental review pursuant to CEQA Guidelines section 15060(c)(3).

 

Fiscal Impact 

The proposed action would appropriate $2,000,000 from TransNet LSI (Fund 404) into the Creek Infrastructure Project for the Via Vera Cruz and Discovery Street elements of the Project (CIP’s 88264 & 88265) and amend the contract with SEMA Construction by the same to $73,357,595.

 

 

Attachment(s)
Resolution XXXX - Resolution Amending Contract 6176 & Amending the CIP budget

 

 

Prepared by:   Isaac Etchamendy, City Engineer

Approved by:   Michelle Bender, City Manager