Skip to main content
“San
File #: TMP-1055    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 5/14/2018 In control: City Council
On agenda: 6/26/2018 Final action:
Title: RESOLUTION NO. 2018-8519 - AWARDING A FIVE YEAR LANDSCAPE MAINTENANCE CONTRACT FOR THE MEDIAN GROUPS A, B AND C
Attachments: 1. Resolution 2018-XXXX

MEETING DATE:                                          

JUNE 26, 2018

 

SUBJECT:                                            

Title

RESOLUTION NO. 2018-8519 - AWARDING A FIVE YEAR LANDSCAPE MAINTENANCE CONTRACT FOR THE MEDIAN GROUPS A, B AND C

Body

 

Recommendation
Recommendation

ADOPT a resolution awarding a five (5) year landscape maintenance service contract to Executive Landscape, Inc. in the amount of $738,640 for median groups A, B and C.

 

Body

Board or Commission Action

Not Applicable

 

Relevant Council Strategic Theme

Dynamic and Responsive Service Delivery

Good Governance

 

Relevant Department Goal

Not Applicable

 

Executive Summary

City staff has publically solicited and reviewed the request for proposals for a five (5) year landscape maintenance contract for the median groups A, B and C. The contract will provide general landscape maintenance services to medians, parkways, and right-of-ways along major corridors within the City. The maintenance consists of general clean-up, pruning, mowing and minor tree trimming. Staff is seeking council approval to award the contract to the most qualified, responsible and responsive bidder.

 

Discussion

Through contract maintenance services, the Public Works Department is responsible for the landscape maintenance of medians and parkways along major corridors within the City such as San Marcos Boulevard, Rancho Santa Fe Road, and Mission Road.  Various combinations of these medians and parkway areas are grouped together for maintenance oversight and referred to as median groups A, B and C.

 

On Wednesday, May 23, 2018, staff publically solicited a request for proposals for the project area.  The contract term is for a five (5) year period and valued at $147,728 per year with a cumulative cost of $738,640 for the term of the contract, not including extra work activities that may be needed on an as-needed basis to maintain a high level of service to the public.

 

On June 13, 2018, the City received two (2) proposals for the services requested.  The table below reflects the proposals received:

 

CONTRACTOR NAME

ANNUAL BID AMOUNT

Executive Landscape, Inc.

$147,728.00

PWLC1, Inc.

$156,000.00

 

Staff has reviewed and evaluated all responsive proposals and has identified Executive Landscape, Inc. as the most qualified, responsible and responsive bidder.  Staff is seeking council approval to award a five (5) year landscape maintenance services contract to Executive Landscape, Inc for a total of $738,640.00

 

Environmental Review

There are no environmental impacts related to this project.

 

Fiscal Impact 

The project is budgeted in the approved Fiscal Year 2017-2018 budget and is funded with General Funds (100), Lighting and Landscape Maintenance District Funds (202) and Citywide CFD 98-02 Funds (205).

 

 

Attachment(s)
Resolution 2018-XXXX

 

 

Prepared by:    Art Sotelo, Public Works Manager- Parks & Landscape

Submitted by:  Jim Chafe, Deputy Public Works Director                     

Reviewed by:  Matt Little, Public Works Director/Deputy City Manager

Approved by:   Jack Griffin, City Manager