File #: TMP-1684    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 2/25/2022 In control: City Council
On agenda: 3/22/2022 Final action:
Title: RESOLUTION NO. 2022-8997 - APPROVING CONSTRUCTION DOCUMENTS AND AUTHORIZING THE CITY MANAGER TO AWARD, FINALIZE, AND EXECUTE CONSTRUCTION CONTRACT DOCUMENTS FOR THE ANNUAL SURFACE SEAL PROJECT FISCAL YEAR 2021 (CIP# ST001)
Attachments: 1. ST001_Resolution_Draft, 2. IP21-00018_Approved Final_031722

MEETING DATE:                                          

MARCH 22, 2022

 

SUBJECT:                                            

Title

RESOLUTION NO. 2022-8997 - APPROVING CONSTRUCTION DOCUMENTS AND AUTHORIZING THE CITY MANAGER TO AWARD, FINALIZE, AND EXECUTE CONSTRUCTION CONTRACT DOCUMENTS FOR THE ANNUAL SURFACE SEAL PROJECT FISCAL YEAR 2021 (CIP# ST001)

Body

 

Recommendation
Recommendation

ADOPT a resolution to approve the construction documents and authorize the City Manager to award, finalize, and execute the construction contract documents for the Annual Surface Seal Fiscal Year 2021 (CIP# ST001).

 

Body

Board or Commission Action 

N/A

 

Relevant Council Strategic Theme

Quality of Life

 

Relevant Department Goal

N/A

 

Executive Summary

On an annual basis, the City uses a Pavement Management Program (PMP) to assign a value, known as a Pavement Condition Index (PCI), representing the current condition of each street segment.  The PCI is utilized to prioritize maintenance and rehabilitation activities.  It is important that preventative maintenance, such as a surface seal, be performed before pavement begins to rapidly deteriorate.  Otherwise, more expensive rehabilitation or reconstruction will be required to bring the pavement to an acceptable condition.  The Annual Surface Seal Fiscal Year 2021 Project (Project) involves a slurry seal and localized pavement repair for portions of Borden Road.

 

Discussion

The Project will surface seal portions of Borden Road between Woodland Parkway and Woodward Street.  The work will include a slurry seal, pavement repair, temporary striping, permanent restriping, buffered bike lane striping, and the installation of new traffic detection loops at existing intersections along the corridor.  The roadway segments shown on the plans were identified by utilizing PCIs from the City’s PMP. 

 

Staff recommends that the City Council approve the construction documents, authorize advertisement for bids, and authorize and delegate the City Manager to award, finalize, and execute the construction contract documents for the Annual Surface Seal Fiscal Year 2021 (CIP# ST001).

 

Environmental Review

The Project is exempt from CEQA pursuant to Section 15301 Class 1 (c) of the CEQA guidelines as is it involves minor improvements and maintenance to an existing roadway without increasing the capacity of the facilities. 

 

Fiscal Impact 

The Project (CIP# ST001) is budgeted in the Fiscal Year 2021-2022 Capital Improvement Projects Budget.

 

 

Attachment(s)
Resolution 2022-8997

Attachment 1: Annual Surface Seal Fiscal Year 2021 (CIP# ST001) Improvement Plans

 

Prepared by:   Michael Rafael, P.E., Senior Civil Engineer

Submitted by:  Lewis Clapp P.E., Principal Civil Engineer                     

Reviewed by:  Isaac Etchamendy P.E., Development Services Director/City Engineer

Approved by:   Jack Griffin, City Manager