Skip to main content
“San
File #: TMP-1478    Version: 1 Name:
Type: Informational Report Status: Agenda Ready
File created: 1/14/2021 In control: City Council
On agenda: 3/23/2021 Final action:
Title: INFORMATIONAL ITEM - SAN MARCOS CREEK SPECIFIC PLAN INFRASTRUCTURE PROJECTS CHANGE ORDER UPDATE

MEETING DATE:                                          

March 23, 2021

 

SUBJECT:                                            

Title

INFORMATIONAL ITEM - SAN MARCOS CREEK SPECIFIC PLAN INFRASTRUCTURE PROJECTS CHANGE ORDER UPDATE

Body

 

Recommendation
Recommendation

NOTE AND FILE this staff report.

 

Body

Board or Commission Action

Not Applicable

 

Relevant Council Strategic Theme

Planning for the Future

Good Governance

 

Relevant Department Goal

Not Applicable

 

Executive Summary

The City is currently constructing the $108MM San Marcos Creek District Specific Plan infrastructure projects (“Project”). The Project construction value at the time of bid was $61,555,365.99. The City has budgeted an industry standard ten percent (10%) construction contingency for the project to pay for unanticipated construction costs. At this time staff desires to update the City Council on change orders encountered since the start of the Project. Provided in this report is a summary of construction change orders to date.  All change orders to date total $1,774,207.12 and are within the identified construction contingency budget.

 

 

Discussion

SEMA was selected as the Contractor to construct the Project at the original contract amount of $61,555,365.99. Over the course of construction various factors can lead to increased costs including but not limited to unforeseen conditions, delays, previously unknown subsurface conditions, design changes, etc. Any item that results in a change to the project is captured in a change order executed between the City and Contractor. To account for potential increases to the project construction cost the City has budgeted an industry standard 10% construction contingency to accommodate these potential increased costs. At this time staff desires to update the Council on change orders to date. Below is a list of completed change orders along with a brief summary of the scope of work each one contains.

 

Change Order 1

Amount: $19,590.69

Scope: Extra work for unforeseen conditions including trash removal, additional stormwater BMPs, work to avoid utility conflicts, and permit registration documents.

 

Change Order 2

Amount: $9,761.90

Scope: Extra work for additional stormwater BMPs.

 

Change Order 3

Amount: $71,369.08

Scope: Updates to controllers on traffic signals to new standards adopted during bid period. This change order also includes a mailbox relocation to avoid conflicts with construction, and various items of extra work for unforeseen conditions.

 

Change Order 4

Amount: $133,401.01

Scope: Temporary bypass for sewer work to allow for construction sewer line while power poles remained in place, extra work for trash and refuse clean-up, additional silt and ESA fencing, and extra work for unforeseen geologic conditions encountered while placing 84” pipe.

 

Change Order 5

Amount: $61,128.44

Scope: Modification of detour road to work around SDGE poles, detour modifications to accommodate utilities, extra work for previously undiscovered subsurface materials, disposal of illicit dumping, and traffic control flagging. 

 

Change Order 6

Amount: $1,478,956.00

Scope: Increases the number of working days by 190 to allow the Contractor sufficient time to perform the work due to delays from utilities. 160 days of that time is considered “compensable” and requires the extension of certain quantities such as time related overhead and site maintenance. 30 days of the change order are considered non-compensable and only extend the completion date but do not require the City to compensate the Contractor.

 

All change orders to date total $1,774,207.12.

 

Environmental Review

The change orders summarized in this staff report are consistent with the approved environmental documents and have been evaluated by staff to not require additional environmental review under the California Environmental Quality Act (CEQA) and National Environmental Policy Act (NEPA). The projects CEQA and NEPA approvals are summarized in Table 1 below:

 

Table 1: Environmental Approval Summary

 

CEQA

APPROVAL DATE

 

 

EIR

07/24/2007

Addendum #1

11/14/2011

Addendum #2

7/16/2015

 

 

NEPA

APPROVAL DATE

ACOE Jurisdiction 404 Permit - Environmental Assessment (EA)/FINDING OF NO SIGNIFICANT IMPACT (FONSI)

2/1/2012

ACOE Jurisdiction Amended 404 Permit - EA/FONSI

2/1/2012

FHWA Caltrans NEPA - CE

1/16/2015

FHWA Caltrans NEPA Re-validation - CE

1/18/2018

 

Fiscal Impact 

Change orders are managed within the approved budget limits of the project. No budget impact is anticipated as part of this informational item.

 

 

Attachment(s)
NONE

 

 

Prepared by:    Isaac Etchamendy P.E., City Engineer                     

Reviewed by:   Dahvia Lynch, Development Services Director

Approved by:   Jack Griffin, City Manager